Table 2 Constructability activities for temporary work and regrouping for integration with design activities.

From: Process for Integrating Constructability into the Design Phase in High-Rise Concrete Buildings: Focused on Temporary Work

Category

Constructability activities

Regrouped activities

(Design stage)

Subdivided activities

Structural methods and surveying

Access roads and pits for permanent measurement

Surveying

(SD) Comparison of alternatives

Measurement method and sensor installation

(DD) Selection of surveying method and locations

Zoning for concrete placement (i.e., construction joints)

Construction methods for structures

(DD) Comparison of alternatives

Rebar placing and splicing

(CD) Method selection and construction planning

Formwork operation method

Evacuation routes and spaces

Evacuation

(DD) Review of evacuation floors and routes

(CD) Selection of evacuation plan

Core construction method

Core construction

(SD) Comparison of alternatives

(DD) Method selection

Circulation for vertical lifting of resources by construction phase

Vertical transportation

(CD) Plan for resource transportation route

Facade protection during structural framework

Facade protection

(CD) Facade protection plan

Vertical transportation of resources

Switching to permanent elevator and platform design

Lifting equipment and concrete pumping

(DD) Comparison of alternatives

Centralization of temporary systems for vertical transportation (temporary bridge, ramp, etc.)

Location of lifting equipment considering finishing work

(CD) Selection of equipment and methods

Concrete pumping method

Other equipment for on-site material handling (gantry cranes, monorails, forklifts, trucks, etc.)

On-site material handling

(CD) Plan for material-handling machinery

Space zoning

Design of the temporary access control system and CCTV layout

Security and ventilation

(CD) Space zoning for security and ventilation systems

Ventilation and dust reduction in working zones during internal finishing

Separation between built and working zones

Separation between zones

(SD) Discussion about separation plan

(DD) Alternatives review

(CD) Selection of optimal plan

Water supply

Switching between temporary and main water tank according to water consumption

Water supply

(DD) Comparison of alternatives

Switching between temporary and main septic tank according to sewage capacity

(CD) Selection of water supply plan

Temporary facilities and services

Standardization and fire protection of the temporary facility

Temporary facilities

(CD) Review of standardization and fire protection

Lighting to prevent collision (T/Cs, airplanes, etc.)

Electricity and lighting

(DD) Comparison of alternatives

Temporary electric power supply and distribution, and electric room

(CD) Selection of electric power supply and lighting plan

  1. SD schematic design, DD design development, CD construction documentation.